Summary
Public Works reported parts arrived to complete repairs at pump house 1 and that TEST INC. and Cahoy Pump Services will perform the work; pump house 2 will be inspected next year.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Public Works Superintendent Jeff Kluck reported a delay in parts for pump house 1 had ended: the part arrived and TEST INC. together with Cahoy Pump Services were scheduled to complete repairs that week.
Kluck said pump house 2 will need to be examined and likely require work next year. The board recorded the maintenance update but did not vote on funding or contract actions during the meeting; the repair work for pump house 1 was described as routine maintenance and operational follow-up.