Board discusses Main Street bid to patch, overlay and fog-seal road
Summary
Trustees reviewed Shaun Gallaher’s bid to patch worst areas of Main Street, overlay 1.75 inches of new roadway, pave the alley behind the fire station and fog-seal to blend old and new pavement using Rebuild and MFT funds.
Get email alerts on the Streets And Roads topic
No spam. Unsubscribe anytime.
The Village of Dakota board discussed a bid from Shaun Gallaher for a Main Street rehabilitation project that would patch the worst sections, place a 1.75-inch overlay, pave the alley behind the fire station and fog-seal to improve the blend between old and new pavement. Trustees noted the project is expected to be paid from the Village’s Rebuild and regular MFT funds.
No formal vote was recorded on the bid during the Feb. 3 meeting; the discussion served to review scope and funding sources. Trustees directed Public Works and relevant officials to evaluate and prioritize items for inclusion in upcoming appropriations planning.