Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Engineer outlines schedule for Teutopolis street and utility projects
Summary
Milano & Grunloh told the board an IEPA funding decision for the Cast Iron Project is expected by July 1; the STU road project likely begins August–September; John Street box culvert will wait for precast materials; Harvester Street preconstruction meeting set for next Tuesday at 10:00 a.m.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Mitch Hardiek of consultant Milano & Grunloh provided a project update to the Teutopolis Board on May 6, laying out funding and construction timelines for several capital projects. He said the village expects an Illinois EPA funding decision on the Cast Iron Project by July 1 and that the STU project is expected to begin construction in August or September.
Hardiek also reported the John Street Box Culvert project will proceed once required precast materials are completed, and that a preconstruction meeting for the Harvester Street project is scheduled for next Tuesday at 10:00 a.m. The board did not request additional action at the meeting beyond acknowledging the timeline.
