Summary

Claycomb Architects and Teal Construction reported the Rockport-Fulton High School is 82% complete on Bond 2022 work, with $32.1 million authorized and substantial completion slated for February 2026.

Claycomb Architects representative Josh Hansen told the Rockport-Fulton Independent School District Board Thursday that "The High School is at 82% complete with $32.1 million authorized and a substantial completion date of February 2026." The presentation, given with Teal Construction representatives Richard Crump and Michael Miller, was part of the monthly Bond 2022 project update.

Board members heard that the high-school project remains the largest active item in the bond package and were provided the authorized budget figure and a target substantial-completion date. The presenters outlined ongoing work and reaffirmed the February 2026 target; no formal board action was required during the update. The update was presented as part of objective 4.3 work on district facilities oversight.