District says high-school project will go vertical next week; site expected watertight by December

Lammersville Joint Unified School District Governing Board · September 19, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Operations staff reported progress on the new high-school construction (slab, framing, trusses) and maintenance updates (pool filters, elevator inspections); the project is on track to be watertight by December and complete in June 2025.

District operations staff said the high-school construction has moved from slab work to framing, with trusses arriving and an expectation that the site will go vertical the week following the meeting. The operations director said trusses are expected on Oct. 14 and the project remains on track to be watertight by December with a finish date targeted for June 2025.

Operations also reported routine maintenance items: elevator inspections, pool filter repairs that required a half day to clear, a vendor change for pool chemicals and ordered windscreens for the tennis courts. Staff listed three current openings in operations (evening custodian, day custodian, clerical), and noted the kitchen remodel had begun with abatement work to address discovered asbestos and lead paint layers; air sampling was planned following abatement before regular construction continues.

Trustees asked no immediate action; staff will continue to monitor the schedule and report progress at future meetings.