Officials say DOT funding intact for Clinton Avenue bridge; land transfer stalled at attorney general

Ellenville Village Board · August 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board reported executed agreements on three of the right-of-way parcels, one parcel requires attorney general approval because it’s religious property, and officials said DOT funding is effectively a 95% grant with a 5% local match.

Village staff provided a project update on the long-running Clinton Avenue bridge replacement, saying right-of-way acquisitions have advanced on several parcels but one parcel remains contingent on the New York attorney general’s office because it involves a religious organization. The chair (S3) said staff is working with state partners and the engineering firm and that DOT review comments are nearly complete. "It is a 95%, effectively funding match to our own 5% local contribution," the chair said.

Staff told the board the federal/state funds for the bridge remain available and that the village will lean on state partners to help the attorney general’s office expedite the transfer. There was no change in the board’s formal funding commitment during the meeting; trustees discussed continuing outreach to DOT and the village engineering firm to keep the schedule on track.