Runway reconstruction in progress; city seeks runway-extension input as Polaris plans flights
Summary
KGM Contractors is completing reconstruction of Runway 16-34 and the parallel taxiway; paving and marking schedules were presented and the city authorized an Airport Master Plan update and TKDA planning services to study a possible runway extension connected to Polaris operations.
Get email alerts on the Airport Infrastructure topic
No spam. Unsubscribe anytime.
City staff reported KGM Contractors is under contract for the Roseau Airport runway reconstruction (contract amount $3,173,095.80). The project schedule for base course and finished surface paving was presented with tentative dates and a prospective runway reopening on July 22, 2026 after marking; final pavement grooving would require a later closure in August. The work includes FAA, State and City cost shares (95% FAA, 2.5% State, 2.5% City).
Staff also said the City will initiate an Airport Master Plan update in 2026 to study a runway extension to accommodate new jet operations proposed by Polaris; the city is seeking a written statement from Polaris that a runway below 5,000 feet would suffice and has approved a reduced-cost proposal from TKDA for airport planning services (reduced from $250,000 to $200,000).