Ladd authorizes up to $15,000 change order to use steel-slag surface on East Cleveland Street
Summary
The Ladd Board authorized President Frank Cattani to sign a change order, not to exceed $15,000, to substitute a carbide/steel-slag surface treatment for the originally bid chip-seal on East Cleveland Street; Engineer Adam Ossola said the alternative may last about ten times longer and costs roughly $10,000 more than chip seal.
Get email alerts on the Streets Surface topic
No spam. Unsubscribe anytime.
The Ladd Village Board on July 13 approved a change order to pursue a steel-slag (carbide aggregate) surface treatment on East Cleveland Street in place of the originally bid tar-and-chip application. Engineer Adam Ossola told the board the carbide-treated surface used by nearby jurisdictions appeared to last substantially longer and did not show asphalt bleeding in hot weather; Ossola said it is "approximately $10,000.00 more than chip seal," and Trustee Dan Nelson noted prior local experience suggests it may be cost-effective over time.
Attorney Patrick Barry recommended instructing the engineer to pursue the change order so the project could continue. Trustee Dan Nelson moved to authorize Village President Frank Cattani to sign a change order to change to steel slag not to exceed $15,000; Trustee Jan Martin seconded and the motion carried 5-0 (Trustee Bernie Victor absent). The board and engineer said they await a firm vendor quote before finalizing the procurement.