Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Facilities topic

No spam. Unsubscribe anytime.

Board approves estimate for radiant heating in town fitness center

Town of Minerva Town Board · December 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved an estimate from Adirondack P&M to install an in-slab hydronic radiant heating system for the Fitness Center tied to the existing boiler, to be completed before the concrete slab is poured. The vote was 4-0.

Supervisor Stephen McNally reported that the parks crew has been cleaning the storage building and that heat must be installed before concrete can be poured in the Fitness Center (Gym). The board approved an estimate from Adirondack P&M for labor and materials to complete the in-slab hydronic radiant heating system from the existing boiler; the resolution passed by roll call 4-0.

The meeting text records the motion as: "to approve RESOLUTION to approve estimate from Adirondack P&M to supply and install all labor and materials to complete the in slab hydronic radiant heating system for the Fitness Center (Gym) from the existing boiler system prior to the concrete slab being poured." The minutes do not list a dollar total for the estimate in the public record attached to the minutes.