The board approved an estimate from Adirondack P&M to install an in-slab hydronic radiant heating system for the Fitness Center tied to the existing boiler, to be completed before the concrete slab is poured. The vote was 4-0.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Supervisor Stephen McNally reported that the parks crew has been cleaning the storage building and that heat must be installed before concrete can be poured in the Fitness Center (Gym). The board approved an estimate from Adirondack P&M for labor and materials to complete the in-slab hydronic radiant heating system from the existing boiler; the resolution passed by roll call 4-0.
The meeting text records the motion as: "to approve RESOLUTION to approve estimate from Adirondack P&M to supply and install all labor and materials to complete the in slab hydronic radiant heating system for the Fitness Center (Gym) from the existing boiler system prior to the concrete slab being poured." The minutes do not list a dollar total for the estimate in the public record attached to the minutes.