Engineer Erin Moore outlines wastewater project timeline, service area and resident cost discussion

Village of Millerton Board of Trustees · January 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineer Erin Moore updated the Millerton Board on the wastewater project, saying phase one will serve the Boulevard district (Town of North East) and the village’s phase one area, and that construction is slated for completion in Spring 2028; funding received to date and estimated annual costs to residents were reported but dollar amounts were not specified.

Erin Moore, an engineer with Tighe and Bond, updated the Village of Millerton Board of Trustees on the planned wastewater project, saying construction is slated to be completed by Spring of 2028. Moore told trustees the presentation covered project funding received to date and the estimated annual cost to residents; the transcript did not specify a dollar amount for that estimate.

Moore reviewed the phase one service area, which includes the Boulevard district in the Town of North East and the village’s phase one service area, and provided an updated project map that the village will upload to its website. The board and attendees from the Town of North East heard that construction timing aims for completion by spring 2028, with further funding and cost details to be finalized as the project advances.