Commissioners approve 10‑month extension of dam engineering services; initial Pine Lake Dam estimate $2.4M
Summary
The Board approved a contract amendment extension for dam engineering services with language revised to a not‑to‑exceed amount of $1,587,100. City Manager said an initial repair estimate for Pine Lake Dam is about $2.4 million; a more precise estimate was expected by Jan. 20.
Get email alerts on the Infrastructure Dams topic
No spam. Unsubscribe anytime.
The Board voted Jan. 6 to extend support engineering services for Sanford/Pine Lake Dam work and revised contract language to cap the amendment at a "not to exceed" $1,587,100 figure.
City Manager Gordon Hargrove told the Board that without the extension, construction and engineering support at Sanford Dam would end and the contractor—Sequoia—could demobilize. He said the project was shortened from 36 to 30 months to reduce costs and that McGill submitted a construction amendment requesting a 10‑month extension at roughly $1.5 million. The Board approved the extension after staff agreed to revise the contract to a not‑to‑exceed amount.
Hargrove also gave a preliminary repair estimate for Pine Lake Dam of about $2.4 million and said a more accurate estimate and construction timeline should be available by Jan. 20. Mayor Jeff Winecoff expressed frustration that contractors brought the extension request late and said engineers had not discussed FEMA reimbursement matters as expected. Commissioner Kim Sherwood sought corrections to contract wording before final execution.
The motion to approve the extension passed 4‑0 with direction to update contract language and ensure appropriate administrative corrections prior to signing.