Council approves change order that trims Southside wastewater plant cost by $956,725
Summary
The Lindale City Council approved Change Order One for the Southside Wastewater Treatment Plant after Brannon Engineering presented plan modifications that reduced construction costs by $956,725. Council voted to accept the change order as presented.
Get email alerts on the Wastewater topic
No spam. Unsubscribe anytime.
Rea Boudreaux of Brannon Engineering presented Change Order One for the Southside Wastewater Treatment Plant, saying modifications to the supplemental plans and specifications produced a net cost reduction of $956,725.00. The council voted to approve the change order on a motion by Councilmember Bob Tardiff and a second by Jerretta Nance Pate.
Council members were advised that some items were removed from the plans as part of the change order and "may be reinstated in the future," according to the staff presentation. No additional public testimony was reported on the item; the approved change order will adjust the project scope and contract value for the contractor CAPPS‑CAPCO Construction, Inc.