Staff reports: Foster, Gerber, Kelner and Ludwig ditch projects updated; Mason Main timeline set

Lorain County Stormwater Management District · February 3, 2026

Summary

Staff told the board Foster Ditch cleaning (H2OH grant) should finish by end of May; Gerber Ditch stabilization needs planting after thaw and an outstanding invoice; Kelner Ditch work and Village improvements on SR303 noted; Mason Main expected in 90–120 days; Ludwig Ditch tree clearing scheduled before ditch work because of bats.

Stormwater staff updated the board on several ongoing maintenance and restoration projects. Don Romancak said the Foster Ditch channel cleaning—funded through an H2OH grant—should be finished by the end of May. He reported Gerber Ditch has been stabilized and only planting remains after thawing; Beckett will be invoiced for the remaining 50% and that money was returned to the commissioners as an advance. Romancak said Kelner Ditch work had started and the Village completed improvements on the south side of SR303.

On timing, staff said Mason Main should be completed within 90–120 days of contract work beginning. Regarding Ludwig Ditch, Romancak said tree clearing will occur prior to ditch work "due to the bats" to avoid impacts. Commissioner David J. Moore observed, "we never hear about the thanks you for the non-flooding of property," noting residents rarely report non-occurrence of flooding after projects.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source