Board hears proposal for blinking four-way stop; change order estimated at $60,000
Summary
A consultant told trustees Wayne County requires a blinking four-way stop at Church and Parke Lane; the proposed change order is $60,000 in hard construction costs with a $3,024 contingency, per the minutes.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
During the information and discussion portion of the meeting, consultant Collin Frink told trustees that Wayne County requires placement of a blinking four-way stop at the corner of Church and Parke Lane. The minutes record a proposed change order of $60,000 for hard construction costs and a contingency of $3,024.
The minutes list the proposal as an information item; no vote or contract award for the change order was recorded at the meeting. Trustees received the estimate as part of the bond/construction update and discussion.