Council approves $19,300 permitting contract for Oyster Plant Park pier repairs
Summary
Council authorized a $19,300 contract with Landau Associates to support JARPA and other aquatic permits for structural repairs to the Oyster Plant Park pier, with permitting expected to take up to nine months and construction targeted for summer 2026 if permits are secured.
Get email alerts on the Parks Infrastructure topic
No spam. Unsubscribe anytime.
The council approved a consultant contract with Landau Associates for $19,300 to assist with permitting for structural repairs at Oyster Plant Park.
Public works staff said Railstar Engineering recommended pile wrapping and other repairs to extend pier life by roughly 50 years, and that the work requires specialized aquatic permitting (the Joint Aquatic Resource Permit Application and associated agency submittals). "This permitting is anticipated—it could take up to about nine months," the presenter said, and noted that Corps of Engineers timing and other agency review may push the schedule. If permitting is completed in time, staff said construction could occur in summer 2026 within regulatory fish windows.
Councilmember Doug Newell moved to approve the consultant contract and the motion carried on a roll-call vote. Staff will return with any permit-driven design updates and a construction bidding timeline as the permitting process progresses.