Superintendent: SVHS gym remodel progressing, expects selections finalized by mid‑March
Summary
Superintendent J. Henry told the board the SVHS gym remodel is progressing, with contractors engaged and final selections (floor graphics, goals, wall pads) expected to be completed by mid‑March.
Get email alerts on the Facilities Remodel topic
No spam. Unsubscribe anytime.
Superintendent J. Henry updated the Board on the SVHS gym remodeling project, saying work is moving forward with several contractors already engaged.
"The SVHS Gym remodeling project is progressing smoothly SO far. We are engaged with the bleacher company, electrical contractor, painter, and floor refinisher," Henry said, and he added that the district is finalizing remaining items including floor graphics, basketball goal and equipment selection, wall pads and doors. He expects those selections and the final schedule to be set by mid‑March.
Architect Lunsford was identified as assisting with the final schedule. Henry characterized the project as one that "we'll be pleased with for many years to come," indicating the district views this as a long‑term facilities improvement.
The board did not take formal action on the project at this meeting but received the construction update as part of the superintendent’s regular report.