Architect drafting Summer 2026 gym remodel schedule; bleacher demolition expected after graduation

Board of Education of Sesser-Valier Community Unit School District No. 196 · January 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District Architect Paul Lunsford is coordinating trades for a Summer 2026 gym remodeling project; district crews will start wall removals after graduation and bleacher demolition is expected to follow, with completion targeted by end of July 2026.

District Architect Paul Lunsford is preparing a detailed schedule for the Summer 2026 gym remodeling project, Superintendent J. Henry said at the Jan. 12 meeting. The plan aims to coordinate trades to avoid conflicts; district staff will begin removing wall items after graduation in preparation for painting and anticipate bleacher demolition shortly thereafter.

Henry said the district is hoping all work will be complete by the end of July 2026. No contractor names, contract amounts, or firm start dates were provided in the minutes; those details remain to be finalized as the architect completes the schedule.

The board did not vote on contract awards or capital budgets at the Jan. 12 meeting; the entry in the superintendent's report served as an informational update.