Wastewater board and permitting office outline pump-station limits amid RV park build-out
Summary
Residents and a wastewater board member warned that sewer pump stations — not just pond capacity — limit how many RV spots the system can serve. Permitting staff said water/wastewater approval letters are required before issuing permits.
Get email alerts on the Sewer Capacity topic
No spam. Unsubscribe anytime.
Landlords and residents told the Police Jury that local sewer infrastructure is strained and that adding more RV spots risks backups. "You can only pump so much crap through a line," said Malcolm Skipper, who described repeated local sewer outages and urged jurors to stop allowing incremental park growth without ensuring sewer capacity.
Anthony Theriault, who identified himself as a wastewater board member, said the core problem is often pump-station capacity rather than pond size: "Just because the pond can hold it, doesn't mean your pump station in your area can." He described planned pump-motor upgrades funded by a grant but said flow between multiple pump stations can still create backups. Robin Morales in the permitting office said the permitting process requires a water-district approval letter documenting sewer and water capacity and the number of spots before the parish issues a permit: "Before we issue a permit, we contact the water district for an approval letter to make sure that they have sewer and water and the number of spots that they're permitting." Jurors discussed case-by-case conditions and said they would work more closely with the wastewater board to confirm capacity before approving more large parks.