Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Electric Infrastructure topic
No spam. Unsubscribe anytime.
Tupper Lake electric: relay repair estimated $100,000; board accepts $10,000 NYSERDA grant
Summary
Black & McDonald relay testing identified Relay #3 as needing rebuild at an estimated $100,000 and out of service for 8–10 weeks; trustees also accepted a $10,000 NYSERDA grant for battery-powered landscaping equipment and approved a small electric account write-off.
Get email alerts on the Electric Infrastructure topic
No spam. Unsubscribe anytime.
Electric Superintendent Michael Dominie told the board that annual relay testing done by Black & McDonald found Relay #3 requires repair; the relay will be de-energized and shipped to Troy, Missouri for rebuilding at an estimated cost of $100,000 and will be out of service for roughly eight to ten weeks while it is rebuilt. Dominie said the village electric system can carry the load during the repair period.
The board unanimously accepted a $10,000 NYSERDA grant to purchase battery-operated landscaping equipment and approved a $42.25 electric account write-off for a deceased customer. Dominie also warned trustees that transmission costs from National Grid and NYPA are anticipated to increase in the near future; he said he will update the board as developments arise. The minutes do not include verbatim participant quotations.
