Residents press city manager over unfinished Main Street; manager says utility coordination delayed construction
Summary
A resident criticized the unfinished connector from behind H-E-B to Lomas Crossing; City Manager Joseph Molis said multiple developers, differing water and sewer utilities, lift-station and water-tower requirements and permit coordination delayed work but agreements and designs are now moving forward.
Get email alerts on the Transportation Projects topic
No spam. Unsubscribe anytime.
During audience Q&A a resident told City Manager Joseph Molis the long-promised road from behind H-E-B to Lomas Crossing remains unfinished after more than a decade: "It's still not completed," the resident said. The resident tied the unfinished connector to frequent accidents and urged the city to accelerate work.
Molis acknowledged the project's importance and explained the delay: multiple property owners and developers control different sections, two water utilities and differing electrical and sewer-service standards required coordination, and updated water-model requirements forced larger lift-station designs. He said the timing changed for developers when water and sewer capacity constraints and a required water tower were added to the plan; those engineering changes increased costs and altered the schedule. Molis said the lift-station design is finished, agreements among parties are close to signing and contractors are lined up for parts of the work. "Main Street is a priority. It's gonna get done," he said, and estimated at least portions could move forward within about a year.
Molis emphasized the city is coordinating multiple permits and that building a single shared lift station for the area is more efficient than three separate facilities; he said sequencing is critical because sewer and lift-station placement affects roadway design. The manager credited developers and said the city would continue to work to accelerate the connection while coordinating with utilities and permitting authorities.