City Hall Drive curb‑ramp work set to start Aug. 17 with 20% contingency

ADA Transition Committee · August 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Norwalk staff told the ADA Transition Committee the Hall Drive curb‑ramp project will begin Aug. 17 and aims to finish by Sept. 30; a 20% contingency was added to the budget and staff will coordinate contractors to avoid conflicts with nearby work.

The City of Norwalk’s ADA Transition Committee was told the Hall Drive curb‑ramp project is slated to begin Aug. 17, with staff projecting an end date of Sept. 30 if work proceeds on schedule. William Nadek, the city’s ADA coordinator, said the Department of Public Works recommended a larger contingency and staff included a 20% contingency in the contract budget.

“There will be an August 17 start… and an end date by September 30,” Nadek said, adding that the project team will coordinate contractors working on adjacent streets to avoid conflicts. He said if the project remains within budget, staff may add additional sidewalk panels between Sections 6 and 7 through a change order with DPW approval.