Gallup council authorizes up to $1.75 million to complete Senior Center construction
Summary
Councilors approved use of up to $1.75 million in previously allocated City and State Aging Bureau funds to finish accessibility, generator, security and landscaping work at the Senior Center so the facility can open for daily use by local and county residents.
Get email alerts on the Community Services topic
No spam. Unsubscribe anytime.
Senior Center Manager Steve Wargo and Project Manager Keegan Mackenzie‑Chavez asked the council to authorize up to $1.75 million in already‑allocated funds to complete construction and site work so the center can open for daily use by city and McKinley County residents.
Wargo detailed ten items to be funded, including curb and sidewalk replacement for ADA compliance, a generator for emergency-shelter function, security fencing, a walking trail, raised planter beds, xeriscape landscaping and patio furniture. Mackenzie‑Chavez explained the term "value engineering" as used in the staff report and said items were prioritized to ensure the facility is complete before opening. Councilor Ron Molina moved to approve the funding authorization; the council voted unanimously to adopt the budget adjustment.
Staff said using the previously allocated City funds and State Aging Bureau grants avoids reverting the money to the General Fund and supports timely completion of the center. The motion authorized staff to expend available grant and city funds for the listed improvements.