Change Order #2 approved for Los Lunas Boulevard; project remains about $1 million under original bid

Board of Trustees of the Village of Los Lunas · June 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved Change Order #2 for the Los Lunas Boulevard extension, adding roughly $453,000 before tax for excavation, pile-depth revisions, storm drain work and other adjustments. Staff said project savings in other areas leave the contract approximately $1 million below original bid totals.

Public Works Director Michael Jaramillo and Molzen Corbin representative Wyatt Kartchner reported construction progress on the Los Lunas Boulevard extension project, including roadway work, paving, curb and gutter installation, and bridge construction across the Rio Grande. Favorable river conditions allowed bridge work to advance ahead of schedule, staff said.

They presented Change Order #2 to address additional excavation of unsuitable materials, detour pavement modifications, revised bridge pile depths, storm drain modifications, testing requirements and material price adjustments. The change order represents an increase of approximately $453,000 before tax; staff said savings in other areas have kept the overall contract about $1 million below the original bid amount. Council approved the change order on a 3–0 vote.

The minutes record continued on-site progress and that construction remains within budget expectations despite the specific change-order increase. Staff did not present a new total contract value in the minutes but described the net position relative to the original bid.