Heart of Iowa says main fiber lines in north Grundy Center due by early September
Summary
Representatives from Heart of Iowa briefed the Grundy Center City Council that most fiber infrastructure north of G Avenue is installed; crews are working on commercial alley connections and household installs will follow, with main lines expected by the beginning of September.
Get email alerts on the Broadband Fiber topic
No spam. Unsubscribe anytime.
Mayor Paul Eberline introduced Jay Duncan and Nathan Butler of Heart of Iowa, who provided an update on the city's fiber-optic installation project.
The presentation said most infrastructure north of G Avenue is installed and crews are now working on commercial-business connections along G Avenue alleys. The project team said its plan is to finish main-line work by the beginning of September, after which household installations will continue. The council received the update as informational; no action was taken.
Finance and scheduling details presented to council included the timeline (main lines by early September) and the shift to household rollouts afterward. No costs or contract changes were presented to the council during the update. The council did not place the matter on the consent agenda for action at this meeting.