Three‑party pretreatment plan would let Skiwall Lodge open while town sewer is built
Summary
Town officials and engineers described a temporary pretreatment system and draft three‑party memorandum of understanding allowing the Skiwall (Joe Minder) Lodge to discharge to Front Street under a high‑level treatment system that would be deeded to the town when the municipal plant is operational.
Get email alerts on the Wastewater topic
No spam. Unsubscribe anytime.
Town and Orda representatives presented a conceptual pretreatment design for wastewater from the Joe Minder Lodge and adjacent pavilion, describing paired equalization tanks, an aerated pre‑equalization tank and a ChromaFlow activated‑sludge treatment train that would reduce nitrogen and organic load before sending an equalized flow to Front Street under a temporary agreement. Presenters said the tanks are sized for interim equalization and that the pretreatment equipment would later be deeded to the town when the municipal wastewater system comes online.
Board members and engineers discussed schedule, site footprint and coordination — especially because the park and youth programs rely on the pavilion and restrooms during the spring and summer. Presenters said the modular tanks can be factory‑assembled and rapidly installed, but careful contract language and a construction coordination plan will be needed to limit disruption. The town agreed to continue working on the draft MOU and to coordinate sequencing so the lodge can open while protecting public use of park facilities.