Johnsburg board votes to authorize phase 2 of North Creek/Cedarwood water project
Summary
After an engineering briefing that described a $5.325 million project partly covered by a 60% WEA grant, the board moved and approved a resolution to authorize proceeding with phase 2; engineers said the award includes a $3 million maximum grant and an estimated local match financing need.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Engineers from CRM Engineering summarized completed work under phase 1 of the North Creek/Cedarwood water project and laid out an estimated phase‑2 scope that would add emergency power and controls, upsized piping on Peaceful Valley Road, redundant well loops and other system improvements. Nick Vandala said the project has a Water Infrastructure Improvement Act (WEA) grant that covers about 60% of eligible costs and that the maximum WEA award for the project was $3,000,000; he said the remaining local match is expected to be financed and that a portion of interest on that loan is currently subsidized.
After discussion about grant stacking, procurement, and user impacts, the board moved a resolution to authorize commencing phase 2 of the WEA project and called the roll; members voted unanimously in favor. The engineers noted the likely timing for design and the potential for staged contracts so higher‑priority items such as controls and emergency power could be accelerated.