Waterworks staff report meter rollout progress and equipment vulnerabilities

Harpers Ferry Town Council · August 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works reported ~750 meter accounts migrated with ~90% automated reads, ongoing projects (Gilbert Street, tank restoration), and a cybersecurity anomaly affecting tank-level modems; staff said some field modems are beyond end-of-life and unpatched, prompting planned replacements and an 'air-gap' mitigation switch.

The town’s Public Works Administrator updated the council on the water-meter rollout and ongoing infrastructure work, and warned of equipment vulnerabilities in field modems that transmit tank-level data.

Public Works reported roughly 750 customer bills have been issued from the new meter collectors and about 90% of accounts now receive automated reads; a small portion still require manual reads. The Gilbert Street project and a phase-3 tank restoration are in final drawing and permitting stages, with bidding expected and work slated to begin this fall.

On cybersecurity, staff described a data anomaly on July 4 involving tank signals and modem settings. The administrator said some modems are 'beyond end of life' and 'not patched,' creating vulnerabilities. To mitigate risk the team installed a switch to disconnect systems (an air gap) when remote connections are not required and plans to update vendor equipment and firmware.

The council directed staff to continue inquiry, bring forward a replacement schedule for outdated modems, and to coordinate modem upgrades with upcoming pump-station and tank projects to avoid duplication of work.