Selectboard authorizes $68,921.12 Pike Industries contract to top‑layer Pine Street
Summary
The board authorized the Road Foreman to accept a $68,921.12 Pike Industries bid to place a top layer on Pine Street; the work will follow recent water‑line work and will be funded from the Paving Reserve.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Selectboard authorized a paving contract for Pine Street at the July 27 meeting. Town staff presented a Pike Industries quote of $68,921.12 to apply a top layer after recent water-line work; funds for the contract are available in the town's Paving Reserve. Jill Marsano explained the water-line logistics and timing for paving; Road Foreman Eric Cota said he will coordinate with Steve Palmer to schedule the work.
Joel Bouvier moved to authorize the Road Foreman to accept Pike Industries' bid of $68,921.12 for the Pine Street top layer. Michelle Perlee seconded the motion and the board voted unanimously to approve the contract. Separately, Eric Cota said he will submit a list of local roads recommended for 1-inch shim spot repairs to address settlement where full paving is not yet scheduled.
The action authorizes procurement and scheduling steps to place the top layer this construction season, contingent on coordination with ongoing water infrastructure work.