Fairgrounds capital projects: 20% of construction budget spent; key roadway work deferred until after fair
Summary
Staff reported about 20% of the construction budget has been spent so far with contingency above 3%; project-level updates included water-line installations on Wingrove, stormwater work near fiber ducts, and full-depth roadway reconstruction on Nontal Road scheduled after the fair.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Ed Henley told commissioners that the campus has reached a meaningful milestone with about 20% of the construction budget expended and an overall contingency that remains above 3 percent, although he cautioned that the financial dashboard is 45–60 days in arrears and numbers may shift.
"As we've now progressed to a meaningful milestone, with 20% of the construction budget that's been allocated now being hit...we still have an overall contingency that's above 3%," Henley said.
Don Collins (Engineering) gave project-level details: installation of 8-inch and 12-inch water lines on Wingrove with required testing, reconnection of a 4-inch private Fairgrounds water line after the fair, ongoing stormwater and coordination with utility owners (AT&T) near fiber infrastructure, and that full-depth roadway reconstruction on Nontal Road will begin only after the fair concludes.
Board members noted the timing of work relative to fair operations and asked staff to keep traffic-control plans and staging details updated as utility and paving work proceeds.