Board hears detailed construction progress report for high school and CTE renovation
Summary
District staff reported demolition is ~98% complete and corridor and classroom finishes are underway; the project is roughly a week ahead in many areas but tile subcontractor delays and coordination with school start remain challenges.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
A presenter provided a progress update on the district's high school and CTE renovation, describing completed demolition, underground plumbing, poured concrete floors and ongoing finishing work in corridors and classrooms.
"The demolition... is about 98% complete," the presenter said, and described that underground plumbing is finished, corridor VCT flooring is being completed, and glass sidelights for large door frames are due to be installed next week. The presenter noted a tile subcontractor delay — the tile worker had promised to start but showed up without materials — and said crews are working to coordinate finishes so areas will be safe and lockable when school begins.
The presenter characterized overall schedule status as roughly "about a week ahead or a week ahead of schedule, not behind, ahead in most areas of the project," and emphasized the need to work around school activities once classes resume. Board members asked clarifying questions about weekend work and coordination with staff and the presenter said the superintendent provided a written summary when he could not attend in person.