Engineer: Victory Park items must be finished before final payment; 2025 street program pegged at $265,000
Summary
The village engineer reported multiple missing items at Victory Park that will delay final payment. He also described a proposed sewer extension route and listed streets included in the 2025 street program with an earlier estimate of $265,000.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Engineer Adam Bunge told the committee that inspectors have identified outstanding work at Victory Park that must be completed before the village will process the final pay request.
Bunge listed what inspectors found: a missing restrictor plate on the storm‑sewer outlet pipe, two 10‑ft benches, an entrance sign, an exit sign and two ADA signs. He said the final pay request was submitted but will be held until all equipment and signage are installed; Fast Signs is scheduled to install signs on Nov. 30.
Bunge also reported that a proposed route for sewer expansion for Four Rivers would follow the basin line farther west into Harrisville Road and then expand north; he said "Kevin will speak with Four Rivers to consider this route." He identified Bibury Drive, Stanton Avenue and Sheridan Grove Drive as streets slated for the 2025 program and cited a previous cost estimate of $265,000.
The minutes do not record a contract change or new appropriation at this meeting; the engineer's report was entered for information and next steps for contractors and Four Rivers were noted.