Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Wastewater topic

No spam. Unsubscribe anytime.

Council approves wastewater work-change directives, pay app #5 and to finance emergency water-main invoice

City Council of the City of Nokomis · August 12, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Benton & Associates presented three wastewater work-change directives with a net deduction of $839.50; the council approved them, approved WWTP pay application #5 for $254,250.00, and agreed to run a $30,232.67 broken-water-main invoice through the project loan.

Cameron Jones of Benton & Associates presented three work change directives for the wastewater treatment plant: change the door size (+$600), increase the breaker size from 250 amps to 300 amps (+$2,766.50), and accept a simplified bar screen (−$4,786), producing net deductions of $839.50. The council approved all three directives.

The council also approved WWTP project pay application #5 in the amount of $254,250.00. Jones reported that Kamadulski had replaced a broken water main and would invoice $30,232.67; after discussion the council voted to run that invoice through the project loan rather than pay it separately. Jones announced the lift-station project bid timeline: bids to be advertised Aug. 16, 2024; pre-bid Aug. 28 at 2:00 P.M.; bid opening Sept. 18, 2024 at 2:00 P.M.