Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Planning And Projects topic

No spam. Unsubscribe anytime.

CRA updates work plan: Innovation Walk progress, Centennial Park blue-light tests and stadium demolition timing

Fort Myers Community Redevelopment Agency Board of Commissioners · January 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

CRA staff briefed the board on the quarterly work plan: LeeTran-managed uniform bus-shelter rollout (9–12 months), Innovation Walk Phase 1 blue-light testing in Centennial Park, Gateway Garden nearing completion, and stadium demolition procurement moving forward with revised funding assumptions.

CRA staff provided the board’s quarterly work-plan update, outlining active projects across Cleveland Avenue, MLK and downtown expansion areas.

Highlights included a uniform ADA-compliant bus-shelter program managed by LeeTran (estimated 9–12 months for permitting and installation), RVI-led Cleveland landscaping currently under FDOT review, the Gateway Garden nearing final landscaping (contractor anticipates completion by early next year) and the Innovation Walk program’s Phase 1 tests for embedded blue-light panels in Centennial Park.

Staff said the Innovation Walk master plan will take about 8–12 months and that the first phase (blue-light testing) is proceeding; they showed sample test panels and said the panels charge during the day and glow at night. On stadium demolition, staff said city procurement is moving forward and clarified a previously anticipated county contribution for demolition (about $1,000,000) is no longer available. The CRA noted it retained budget authority for partial demolition funding and will coordinate with the city on next steps.

Staff also reviewed program status for the residential paint program (30 sign-ups, 12 completed so far in expansion area) and said three home-preservation projects with Habitat for Humanity are moving through the pipeline. The board received the update for information; no formal votes were required.