Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Planning Timeline topic
No spam. Unsubscribe anytime.
Twisp sets schedule: 90% design due Sept. 5, budget final in October, bids in early 2026
Summary
Minutes set key deadlines: final 90% construction documents due by Sept. 5; budget finalization expected in October; construction bidding targeted for early 2026; August meeting to decide scope of streetscape elements for grant matching.
Get email alerts on the Planning Timeline topic
No spam. Unsubscribe anytime.
The Creative District’s minutes set a timetable for final design, budgeting, and procurement tied to the capital grant and streetscape work. The record states that a final 90% construction document set is due by September 5, with budget finalization expected in October and construction planned to go out to bid in early 2026.
The minutes identify the August meeting (last Thursday of August) as the key decision point to determine the number and scope of bike racks, benches, sculpture pads, and other creative elements that will be included and which of those items can be counted toward grant match. The timeline ties design completion to the grant’s match-eligibility and procurement schedule.
Staff and volunteers will use the coming weeks to refine quantities and costs so the budget can be finalized in time for application and bidding milestones.
