Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Maintenance Infrastructure topic

No spam. Unsubscribe anytime.

Staff: recurring fire-station flooding linked to incorrectly sized pipe

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported recurring flooding at a fire station and said a contractor installed a 6-inch pipe into an 8-inch line instead of matching 8-to-8, and that they are working to 'rectify' the sewer line and remove roof trays at the rear.

When asked if he had anything further, a staff member described repeated flooding at a fire station and attributed the problem to an installation issue. The staff member said, "It keeps flooding," and described contractor work where "they shoved a 6 inch pipe into an 8 inch" instead of matching an 8-to-8 connection; staff said they are working to remove roof trays at the rear and to rectify the sewer-line configuration.

The chair noted this flooding had occurred multiple times in the recent past, asking, "So that's the 3rd time now it's flooded in about 2 weeks?" Staff confirmed they were working with the contractor to fix the configuration. The meeting record does not show a formal directive or a timeline beyond staff's statement that they are attempting to rectify the situation.