Project team summarizes PCOs and change-order costs; several items lower or raise the balance
Summary
Presenters reviewed a set of PCOs including an AV credit, an overhead-door adjustment ($7,910), telecom and clock/speaker locations ($19,337), locker-size adjustments ($16,457), ductwork removal ($10,913) and electrical make-safe work ($17,446); presenters estimated remaining costs in the low hundreds of thousands.
Get email alerts on the Change Orders topic
No spam. Unsubscribe anytime.
Project presenters (S5, S7) walked the committee through recent Potential Change Orders (PCOs). Items included AV/TV location revisions that produced a small credit (about $96), an overhead door modification costing $7,910, added telecom locations and fixtures at $19,337, locker-size reductions ($16,457), ductwork removal ($10,913) and electrical make-safe work at $17,446. Presenters said the project remains in typical PCO review and that some items were reduced after negotiation.
Committee members noted the remaining corridor and finish areas still carry outstanding work; presenters estimated remaining change-order exposure in the low hundreds of thousands and asked staff to have final totals ready for the next review.