High-school FF&E and tech numbers reported; server quote over $100,000 prompts urgent review

Public Building Committee · August 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project staff reported FF&E at $4,124,618.94 and technology at $1,966,305.24, leaving a roughly $20,000 net delta; committee members raised an urgent concern about town/server capacity with quotes for additional server work exceeding $100,000 and asked that the issue come to the PBC within two weeks.

Presenter (S3) provided the project's final equipment and tech totals: "our we've we ended up with, $4,124,618.94 for FFNE," S3 said, and reported technology at $1,966,305.24. S3 added that technology came in about $82,000 over budget while FF&E was roughly $59,000 under, leaving a net delta of approximately $20,000.

The committee discussed a separate but related problem: town server capacity. S3 said recent quotes to upgrade town/server capacity to support new-school systems have been over $100,000, and members debated whether the cost is a town-wide infrastructure need or a requirement created by the new high school. The committee directed staff to schedule an expedited review with Todd, Frank and Jason, to have Jason confirm technical needs and to bring a recommendation to the PBC meeting in two weeks so procurement and budget implications can be resolved.