Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Technology Budget topic
No spam. Unsubscribe anytime.
High-school FF&E and tech numbers reported; server quote over $100,000 prompts urgent review
Summary
Project staff reported FF&E at $4,124,618.94 and technology at $1,966,305.24, leaving a roughly $20,000 net delta; committee members raised an urgent concern about town/server capacity with quotes for additional server work exceeding $100,000 and asked that the issue come to the PBC within two weeks.
Get email alerts on the Technology Budget topic
No spam. Unsubscribe anytime.
Presenter (S3) provided the project's final equipment and tech totals: "our we've we ended up with, $4,124,618.94 for FFNE," S3 said, and reported technology at $1,966,305.24. S3 added that technology came in about $82,000 over budget while FF&E was roughly $59,000 under, leaving a net delta of approximately $20,000.
The committee discussed a separate but related problem: town server capacity. S3 said recent quotes to upgrade town/server capacity to support new-school systems have been over $100,000, and members debated whether the cost is a town-wide infrastructure need or a requirement created by the new high school. The committee directed staff to schedule an expedited review with Todd, Frank and Jason, to have Jason confirm technical needs and to bring a recommendation to the PBC meeting in two weeks so procurement and budget implications can be resolved.

