City waits on pole and National Grid scheduling for Carolina–Ridge traffic light

Lackawanna City Council · November 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Senior foreman Dan Durkin told the council contractor CATCO is waiting on a traffic-signal arm pole expected mid–late November; after pole installation National Grid must schedule electric work to activate the light.

Senior foreman Dan Durkin provided an update on the Carolina and Ridge Road traffic-signal project, telling councilors the contractor (CATCO) is waiting for the signal arm pole, which the factory estimated would be manufactured and ready in mid to late November.

Durkin said contractors can install poles quickly once received, but the city must wait for National Grid to schedule the line crew to hook up permanent electric service. He emphasized the city has limited control over National Grid's scheduling and that the project remains contingent on the pole delivery and the utility's scheduling.