Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Canopy Project topic
No spam. Unsubscribe anytime.
Solect schedules Ames Field canopy mobilization for Aug. 10; completion and PTO dates projected
Summary
Solect told MSOC mobilization for the Ames Field/Pond Street canopy solar project is scheduled for Aug. 10, with most construction after Labor Day, completion by Dec. 26 and Eversource PTO anticipated by March 2027; a parking replacement plan was agreed with schools and DPW.
Get email alerts on the Canopy Project topic
No spam. Unsubscribe anytime.
The committee reviewed logistics and schedule for the Ames Field/Pond Street canopy solar project. Allen Giles said Solect plans to mobilize Aug. 10, with the bulk of construction after Labor Day. Town and school officials resolved a plan to provide replacement parking during construction. Solect forecasted construction completion "by Dec. 26" and anticipated Eversource permission to operate by March 2027.
Committee members emphasized coordination with the School Department, DPW and Recreation for parking logistics and timing. The minutes record the mobilization date (Aug. 10), the construction window (after Labor Day) and the projected milestones; the transcript does not specify the calendar year for the Dec. 26 completion date in that line, though surrounding items reference 2026 and 2027.
