District reports progress on parking, ADA restrooms, track and roofs; track surfacing requires 21-day cure

Eastern Greene Schools Board of Trustees · August 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff reported the high-school parking lot is about 90% complete, ADA restrooms by athletic fields finished, roofing and track projects progressing with a required 21-day curing period before track surface installation, and playground demolition slated for mid-September.

District staff provided a detailed construction update covering multiple campus projects and timelines.

"The parking lot paving project is approximately 90% complete on the high school campus," the staff member said, noting remaining striping work and minor grading. He reported ADA restrooms near the soccer and football fields are finished and available for use. On the track project he described recent weather-related stabilization work and said concrete ribbon and curb work were underway; the track surface application was scheduled for the week of Aug. 21.

The staff member added a technical note: after new asphalt is laid, the surface requires a 21-day curing period before installation of the latex rubber track surface. Roof work at the elementary and middle school campuses continues; the early learning center is in punch-list phase and Jasper Lumber was expected to finish remaining items within three weeks. Playground demolition and installation for infant/toddler and 3-5 year-old areas were expected to begin in mid-September.