Summary
The board voted to approve option 2, installing 95% AFUE propane lead/lag boilers for Town Hall (approx. $24,899) to replace aging equipment; funding will come from the Town Hall Improvements Capital Reserve Fund and staff will issue purchase orders.
The Select Board reviewed two proposals to address failing boilers and heating equipment at Town Hall: a repair option (~$24,890 for boiler replacement) and a propane lead/lag system (95% AFUE, proposed at roughly $24,899). Member S4 moved to select option 2 (propane system) and the board approved the motion by voice vote. S4 said his experience favored the propane option and noted efficiency benefits: "Well, because I've had very close experience... the propane was really better."
Town staff said that funds would be taken from the Town Hall Improvements Capital Reserve Fund and that the purchase order process would be used to track commitments. The board instructed staff to coordinate with trustees for fund availability and to process the PO so the work may proceed once contracting and scheduling are finalized.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.