Wall Street project 75% complete; board approves $249,920 Pay Application #8
Summary
Delta 3 Engineering reported Wall Street work is 75% complete; the board approved Pay Application #8 to JI Construction for $249,920 and Digman revised the expected project overrun to about $55,000 after the village added roughly $140,000 in extras.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Delta 3 Engineering provided an infrastructure update on the 2024 project: Wall Street was described as about 75% complete with cleanup and landscaping scheduled by June 6. Mark Digman noted earlier estimates that the project would exceed contract by about $70,000 in December, but that estimate had improved to roughly $55,000 after accounting for village-directed extras.
Digman’s note itemized village additions that contributed to the higher outlay — for example, fill site work (~$66,000), paving on West Court Street (~$40,000), storm sewer on Spruce Road (~$15,000), additional new water services and laterals (~$15,000) and tree removals (~$4,000), for an approximate total of $140,000 in add-ons. The board voted to approve Pay Application #8 to JI Construction for paving in the amount of $249,920; the motion passed unanimously.
The approval allows the contractor to proceed toward final paving work while the village continues to reconcile final contract changes and pursue remaining close-out tasks.