Delta 3: Bloomington wastewater plant needs multiple upgrades; plan and grants targeted for 2026–2029

Village of Bloomington Board · November 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Consultant Jordan Fure presented a wastewater treatment facility evaluation showing the plant (1983) is at about 57% design flow but must meet newer DNR limits (ammonia, E. coli, PFAS, chlorides, phosphorus); Delta 3 recommended major equipment replacements and a project timeline with grant applications and a $5,000 Focus on Energy reimbursement.

Jordan Fure of Delta 3 presented an evaluation of Bloomington's wastewater treatment plant, summarizing capacity and regulatory changes since the plant's 1983 construction. He said the plant is operating at roughly 57% of design flow but must comply with newer DNR requirements for ammonia, fecal coliform (now E. coli), PFAS, chlorides and total phosphorus.

The evaluation identified several near‑term and long‑term needs: replace an obsolete 1983 motor control center (MCC), rehabilitate the aeration tank building, replace the high‑wear comminutor, upgrade the generator (currently powering only blower #1), replace the chlorine disinfection system with UV, construct a new sludge storage tank outside the floodplain, and add dissolved oxygen probes and energy‑efficient blowers. Jordan recommended variable frequency drives for the MCC and a mechanical headworks screen with an automatic bagger. He said Delta 3 will send a final report in December, the village will receive a $5,000 reimbursement through Focus on Energy, and Delta 3 will return in February 2026 to discuss facility‑plan priorities and costs ahead of anticipated 2027 plans/specs and 2028–2029 construction.