District facilities reports progress on roofs, HVAC, elevators and upcoming bids

Montgomery Public Schools Board of Education · August 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff updated the board on multiple capital projects: Davis and Danley HVAC work, near completion of Forest Avenue and South Lawn roofs, JAG athletic improvements, elevator renovation pre‑bid and a delayed field house bid to Sept. 1 for additional electrical engineering work.

Facilities director Chad Anderson reviewed a portfolio of projects across the district, reporting that the Davis Elementary HVAC phase 2 is complete and phase 3 is starting; Forest Avenue and South Lawn roof replacements are approximately 90% complete; and the Danley HVAC renovation continues in multi‑phase work.

Anderson described a JAG athletic improvement project (curb and gutter 95% complete), epoxy flooring accomplishments, and an upcoming preconstruction conference for the JAG elevator renovation that will also upgrade fire alarm coverage in the building. He said a detailed electrical update pushed the JAG field house bid to Sept. 1 to allow the electrical engineer to update submittals.

Board members asked clarifying questions about project sequencing and disruption mitigation during in‑school work. Anderson said crews are coordinating to minimize classroom disruption and anticipate phased work to avoid broad interruptions to students.