Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Energy topic
No spam. Unsubscribe anytime.
Board accepts two solar bids on record, asks staff to analyze options
Summary
The board opened and accepted two bids for solar panels at the highway garage (Apex Energy and ABK Solar) for further analysis; Apex's net was reported at about $149,212 while ABK's net cost was discussed near $176,568 after credits. Members agreed to review and return with a recommendation.
Get email alerts on the Energy topic
No spam. Unsubscribe anytime.
The Town Board accepted two bids for solar panels at the highway garage and tasked staff to compare them in detail.
Supervisor Stanley reported numbers from the two bids: ABK Solar’s bid carried a service credit and, after credits, the board discussed a figure the transcript recorded as a net cost of about $176,567.95; Apex Energy’s bid showed a net cost the board discussed at roughly $149,212. "So we have 2 bids... The net cost would be a $176,567.95" the supervisor said when reading the ABK numbers and then identified Apex’s net figure.
Board members voted to accept the bids to the record and asked staff and the climate-smart task force to return at the next meeting with an analysis of lifecycle costs, projected credits and deadlines tied to bid validity. The supervisor said if there is a deadline on either quote the board may convene a special meeting; otherwise the board will review side‑by‑side information and select a vendor later.

