Board presents $2.03M Waterloo bid package but postpones final funding decision after members ask for enrollment and utilization plan

Monroe Public Schools Board of Education · December 12, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Miss Shook presented multiple base bids totaling up to $2,033,476 for Waterloo bond work; after extended debate about declining enrollment and a lack of a clear long-term plan for the building, the board voted to postpone the funding/award decision and asked staff for enrollment-count data and a utilization plan.

The board heard a detailed presentation of the Waterloo bond-work base bids and a recommended package totaling $2,033,476 to be funded from the bond capital projects fund. Miss Shook summarized multiple line items and contractors, including a $108,900 bid from Chrisland Contractors and a $1,039,000 bid listed for a second contractor; the full package amount was presented as not to exceed $2,033,476.

Several board members raised concerns about spending $2 million on Waterloo while district enrollment has been declining for several years. One member noted the district had recently invested in air-conditioning, mechanical and electrical upgrades at the building and questioned whether the district should proceed without a clear long-term plan for the facility. Board members asked for enrollment data, projections and a clearer plan for Waterloo’s intended use (examples discussed included preschool or K–6 use), and several suggested holding a work session to examine utilization before committing bond dollars.

After debate, a motion to postpone the funding decision to allow staff to compile enrollment-count data from the district’s count day and to present a clear utilization and business plan for Waterloo was moved, seconded and carried. The board directed staff to return with projected population data, clarification of grade-level uses and facility utilization information at a future meeting (board meeting number 17/October). Miss Shook and staff will prepare the requested materials.