Dakota approves WWTP change order; completion date pushed to Oct. 14

Village of Dakota Board · August 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved Change Order #1 for the wastewater treatment plant, moving the completion date from July 5 to Oct. 14 and extending the access road; the board reviewed a 31-item punch list with 13 items completed and will recheck before final payment.

On a motion by Jeremy Knox, seconded by Ken Vrazsity, the Village of Dakota board approved Change Order #1 for the wastewater treatment plant project. The change order moves the project completion date from July 5 to Oct. 14 and extends the access road to improve meter access; the board was told there is no price change tied to the order.

Trustees reviewed the WWTP punch list: 31 items in total with 13 completed to date. The board said it will re-review the remaining punch list items before any final payment is disbursed and will solicit quotes for a protective structure to be placed over pumps to limit wear and tear.