Dakota trustees say wastewater project still incomplete; final walkthrough planned

Village of Dakota Board · June 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees reported the wastewater treatment project missed April and a revised May completion, citing a ComEd hookup and back-ordered pipe fittings; a trustees' final walkthrough will be scheduled and litigation related to the water tower repairs is underway.

Board members told residents June 2 that the village's wastewater treatment facility project is not yet complete. The project was supposed to be finished by April 30 and a requested May 16 finish date was also missed; delays were attributed to a ComEd hookup and pipe fittings that were back-ordered but are now complete.

Village President Jon Riley said Willett Hofmann and contractor Kelsey are coordinating to set a firm final date and that he will request a final walk-through with the trustees. Trustees also discussed separate related infrastructure items: the water tower repair expected to start in mid-June and litigation the village is pursuing related to that work, plus planned Main Street repairs and a $24,999 sidewalk budget for bids.