Dakota board declines pay application for IEPA project request totaling $246,652.37; wants 10% retained from contractor
Summary
Trustees reviewed IEPA PWSL 17-4260 Request #14 for $246,652.37 (including Kelsey Excavating Pay App #11 for $244,454.72 and WH & A invoice $2,197.65) and decided not to move forward with the pay application; they indicated a desire to retain 10% from Kelsey Excavating until completion.
Get email alerts on the Infrastructure Wastewater topic
No spam. Unsubscribe anytime.
During new business, Matt Hansen presented an updated punch list for the wastewater treatment facility and introduced IEPA PWSL 17-4260 Request #14 totaling $246,652.37, which included WH & A Invoice #40173 for $2,197.65 and Kelsey Excavating Pay Application #11 for $244,454.72. After discussion, the board opted not to approve the pay application at this time and stated it wants to keep a 10% retainage from Kelsey Excavating until all contracted work is complete.
Minutes do not record a formal motion approving the pay application; they record the board's decision not to move forward. Trustees indicated some remaining punch-list items may wait until spring, and the board expects remaining project oversight and retentions to be addressed before final payments are released.